The works are to be carried out in two distinct
blocks with Phase One Inception Works now completed before the
commencement of any building works. Works included in phase one
were relocation of the distribution board and server from the
current admin area, rearrangement of site access to separate the
contractors operations from the school, realignment of site
boundary fence and the formation of a contractors compound, site
area and access road, the installation of a new electric supply,
the realignment of water and I.T. services, the formation of new
wildlife pond, the formation of temporary admin. office within the
existing servery room and the installation of a temporary boiler
house.
The building and external works
are to be completed in two phases. Phase One will include the
demolition of the existing admin area and the erection of a new
single storey extension and formation of phase one external works.
Phase Two includesworks to existing infants school demolition of
the former servery area and erection of new classrooms and group
rooms, removal of asbestos and demolition of the two storey former
Junior School and completion of external
works.
Construction is traditional brick/block with a
steel frame to the school hall.